The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position.

AttributesValues
rdf:type
rdfs:label
  • Point of total assumption (fr)
  • Punto di carico totale (it)
  • Point of total assumption (en)
rdfs:comment
  • The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position. (en)
  • Le point of total assumption (PTA) est un point sur la courbe de coût déterminé par les éléments contractuels associés avec un contrat au forfait (à prix fixe, par opposition à un contrat en régie) avec intéressement Fixed Price plus Incentive (FPI), au-dessus duquel le fournisseur (vendeur) supporte tous les coûts liés à un surcoût. Le vendeur assume tous les risques de coût à partir de ce point PTA, puisque chaque euro de surcoût se traduit par une baisse de un euro de la marge bénéficiaire. Et que dès que le coût dépasse ce PTA, le montant maximum que l'acheteur paie est le prix plafond. (fr)
  • Il termine è mutuato dalle discipline tecnico-gestionali, manageriali e giuridiche degli Stati Uniti regolanti la materia delle grandi opere e, segnatamente, delle opere pubbliche. Nella gestione dei progetti e, più specificamente, nei contratti FPIF il punto di carico totale degli ovverrun di costo (PTA, Point of Total Assumption) è la variabile in corrispondenza della quale l'eventuale incremento di costo è sopportato interamente dall'appaltatore. Nel contesto, pertanto, il sostantivo inglese assumption ha il significato di "carico" o "accollo". Prima del raggiungimento del PTA, l'eventuale overrrun di costo è ripartito in varia misura tra le parti contrattuali: nelle grandi commesse si prevede, normalmente, una partecipazione calcolata al rischio di aumento dei costi tra cliente (buy (it)
foaf:depiction
  • http://commons.wikimedia.org/wiki/Special:FilePath/PMP_FPIF_Contracts_-_BAC_exceeds_PTA.jpg
dcterms:subject
Wikipage page ID
Wikipage revision ID
Link from a Wikipage to another Wikipage
Link from a Wikipage to an external page
sameAs
dbp:wikiPageUsesTemplate
thumbnail
has abstract
  • The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position. (en)
  • Il termine è mutuato dalle discipline tecnico-gestionali, manageriali e giuridiche degli Stati Uniti regolanti la materia delle grandi opere e, segnatamente, delle opere pubbliche. Nella gestione dei progetti e, più specificamente, nei contratti FPIF il punto di carico totale degli ovverrun di costo (PTA, Point of Total Assumption) è la variabile in corrispondenza della quale l'eventuale incremento di costo è sopportato interamente dall'appaltatore. Nel contesto, pertanto, il sostantivo inglese assumption ha il significato di "carico" o "accollo". Prima del raggiungimento del PTA, l'eventuale overrrun di costo è ripartito in varia misura tra le parti contrattuali: nelle grandi commesse si prevede, normalmente, una partecipazione calcolata al rischio di aumento dei costi tra cliente (buyer) ed impresa (seller), definita "BSR" (Buyer's Share Ratio). (it)
  • Le point of total assumption (PTA) est un point sur la courbe de coût déterminé par les éléments contractuels associés avec un contrat au forfait (à prix fixe, par opposition à un contrat en régie) avec intéressement Fixed Price plus Incentive (FPI), au-dessus duquel le fournisseur (vendeur) supporte tous les coûts liés à un surcoût. Le vendeur assume tous les risques de coût à partir de ce point PTA, puisque chaque euro de surcoût se traduit par une baisse de un euro de la marge bénéficiaire. Et que dès que le coût dépasse ce PTA, le montant maximum que l'acheteur paie est le prix plafond. Cependant, tant que le coût reste compris dans la zone entre le PTA et le prix plafond, le vendeur continue à gagner de l'argent. En revanche, dès que le coût dépasse ce prix plafond, le vendeur commence à perdre de l'argent sur le contrat correspondant. Le PTA est donc le coût à partir duquel la rentabilité du contrat baisse pour le vendeur, devenant nulle lorsque le coût atteint le prix plafond, et négative au-delà. (fr)
gold:hypernym
prov:wasDerivedFrom
page length (characters) of wiki page
foaf:isPrimaryTopicOf
is Link from a Wikipage to another Wikipage of
is Wikipage redirect of
is Wikipage disambiguates of
is foaf:primaryTopic of
Faceted Search & Find service v1.17_git139 as of Feb 29 2024


Alternative Linked Data Documents: ODE     Content Formats:   [cxml] [csv]     RDF   [text] [turtle] [ld+json] [rdf+json] [rdf+xml]     ODATA   [atom+xml] [odata+json]     Microdata   [microdata+json] [html]    About   
This material is Open Knowledge   W3C Semantic Web Technology [RDF Data] Valid XHTML + RDFa
OpenLink Virtuoso version 08.03.3330 as of Mar 19 2024, on Linux (x86_64-generic-linux-glibc212), Single-Server Edition (61 GB total memory, 42 GB memory in use)
Data on this page belongs to its respective rights holders.
Virtuoso Faceted Browser Copyright © 2009-2024 OpenLink Software