The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position.

Property Value
dbo:abstract
  • The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position. (en)
  • Il termine è mutuato dalle discipline tecnico-gestionali, manageriali e giuridiche degli Stati Uniti regolanti la materia delle grandi opere e, segnatamente, delle opere pubbliche. Nella gestione dei progetti e, più specificamente, nei contratti FPIF il punto di carico totale degli ovverrun di costo (PTA, Point of Total Assumption) è la variabile in corrispondenza della quale l'eventuale incremento di costo è sopportato interamente dall'appaltatore. Nel contesto, pertanto, il sostantivo inglese assumption ha il significato di "carico" o "accollo". Prima del raggiungimento del PTA, l'eventuale overrrun di costo è ripartito in varia misura tra le parti contrattuali: nelle grandi commesse si prevede, normalmente, una partecipazione calcolata al rischio di aumento dei costi tra cliente (buyer) ed impresa (seller), definita "BSR" (Buyer's Share Ratio). (it)
  • Le point of total assumption (PTA) est un point sur la courbe de coût déterminé par les éléments contractuels associés avec un contrat au forfait (à prix fixe, par opposition à un contrat en régie) avec intéressement Fixed Price plus Incentive (FPI), au-dessus duquel le fournisseur (vendeur) supporte tous les coûts liés à un surcoût. Le vendeur assume tous les risques de coût à partir de ce point PTA, puisque chaque euro de surcoût se traduit par une baisse de un euro de la marge bénéficiaire. Et que dès que le coût dépasse ce PTA, le montant maximum que l'acheteur paie est le prix plafond. Cependant, tant que le coût reste compris dans la zone entre le PTA et le prix plafond, le vendeur continue à gagner de l'argent. En revanche, dès que le coût dépasse ce prix plafond, le vendeur commence à perdre de l'argent sur le contrat correspondant. Le PTA est donc le coût à partir duquel la rentabilité du contrat baisse pour le vendeur, devenant nulle lorsque le coût atteint le prix plafond, et négative au-delà. (fr)
dbo:thumbnail
dbo:wikiPageExternalLink
dbo:wikiPageID
  • 8501281 (xsd:integer)
dbo:wikiPageLength
  • 6061 (xsd:nonNegativeInteger)
dbo:wikiPageRevisionID
  • 1069342043 (xsd:integer)
dbo:wikiPageWikiLink
dbp:wikiPageUsesTemplate
dcterms:subject
gold:hypernym
rdf:type
rdfs:comment
  • The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun. The seller bears all of the cost risk at PTA and beyond, due to a dollar for dollar decrease in profit beyond the costs at the PTA. In addition, once the costs on an FPI contract reach PTA, the maximum amount the buyer will pay is the ceiling price. Note, however, that between the cost at PTA and when the cost equals the ceiling price, the seller is still in a profitable position; only after costs exceed the ceiling price is the seller in a loss position. (en)
  • Le point of total assumption (PTA) est un point sur la courbe de coût déterminé par les éléments contractuels associés avec un contrat au forfait (à prix fixe, par opposition à un contrat en régie) avec intéressement Fixed Price plus Incentive (FPI), au-dessus duquel le fournisseur (vendeur) supporte tous les coûts liés à un surcoût. Le vendeur assume tous les risques de coût à partir de ce point PTA, puisque chaque euro de surcoût se traduit par une baisse de un euro de la marge bénéficiaire. Et que dès que le coût dépasse ce PTA, le montant maximum que l'acheteur paie est le prix plafond. (fr)
  • Il termine è mutuato dalle discipline tecnico-gestionali, manageriali e giuridiche degli Stati Uniti regolanti la materia delle grandi opere e, segnatamente, delle opere pubbliche. Nella gestione dei progetti e, più specificamente, nei contratti FPIF il punto di carico totale degli ovverrun di costo (PTA, Point of Total Assumption) è la variabile in corrispondenza della quale l'eventuale incremento di costo è sopportato interamente dall'appaltatore. Nel contesto, pertanto, il sostantivo inglese assumption ha il significato di "carico" o "accollo". Prima del raggiungimento del PTA, l'eventuale overrrun di costo è ripartito in varia misura tra le parti contrattuali: nelle grandi commesse si prevede, normalmente, una partecipazione calcolata al rischio di aumento dei costi tra cliente (buy (it)
rdfs:label
  • Point of total assumption (fr)
  • Punto di carico totale (it)
  • Point of total assumption (en)
owl:sameAs
prov:wasDerivedFrom
foaf:depiction
foaf:isPrimaryTopicOf
is dbo:wikiPageDisambiguates of
is dbo:wikiPageRedirects of
is dbo:wikiPageWikiLink of
is foaf:primaryTopic of
Powered by OpenLink Virtuoso    This material is Open Knowledge     W3C Semantic Web Technology     This material is Open Knowledge    Valid XHTML + RDFa
This content was extracted from Wikipedia and is licensed under the Creative Commons Attribution-ShareAlike 3.0 Unported License