Building Enclosure Commissioning (BECx) (sometimes 'envelope' is used instead of 'enclosure') is a strict quality-focused process wherein the energy performance of a facility, system or assembly is evaluated and verified against defined objectives and criteria. The process itself is carried out by a commissioning team which uses reliable and accurate measures to verify that the project is meeting specific quality requirements outlined by the owner of the project. The commissioning process begins at project inception and runs through different construction phases, which include a pre-design phase, pre-construction phase and construction phase. Once the construction is finished, the commissioning process continues and becomes an ongoing routine in the life of the facility. Specific informati

Property Value
dbo:abstract
  • Building Enclosure Commissioning (BECx) (sometimes 'envelope' is used instead of 'enclosure') is a strict quality-focused process wherein the energy performance of a facility, system or assembly is evaluated and verified against defined objectives and criteria. The process itself is carried out by a commissioning team which uses reliable and accurate measures to verify that the project is meeting specific quality requirements outlined by the owner of the project. The commissioning process begins at project inception and runs through different construction phases, which include a pre-design phase, pre-construction phase and construction phase. Once the construction is finished, the commissioning process continues and becomes an ongoing routine in the life of the facility. Specific information regarding the commissioning process is outlined in the ASHRAE Guideline 0-2005: The Commissioning Process. This and several other technical support guidelines to the Guideline 0-2005 document provide specific information related to the commissioning process. Typical Commissioning Objectives: * Heat Flow * Air Flow * Noise * Fire * Light * Infrared * Ultraviolet * Rain Penetration * Moisture * structural performance * Durability * Security * Reliability * Aesthetics * Value * Constructability * Maintainability * Sustainability (en)
dbo:wikiPageID
  • 32910374 (xsd:integer)
dbo:wikiPageLength
  • 2543 (xsd:nonNegativeInteger)
dbo:wikiPageRevisionID
  • 795684323 (xsd:integer)
dbo:wikiPageWikiLink
gold:hypernym
rdf:type
rdfs:comment
  • Building Enclosure Commissioning (BECx) (sometimes 'envelope' is used instead of 'enclosure') is a strict quality-focused process wherein the energy performance of a facility, system or assembly is evaluated and verified against defined objectives and criteria. The process itself is carried out by a commissioning team which uses reliable and accurate measures to verify that the project is meeting specific quality requirements outlined by the owner of the project. The commissioning process begins at project inception and runs through different construction phases, which include a pre-design phase, pre-construction phase and construction phase. Once the construction is finished, the commissioning process continues and becomes an ongoing routine in the life of the facility. Specific informati (en)
rdfs:label
  • Building enclosure commissioning (en)
owl:sameAs
prov:wasDerivedFrom
foaf:isPrimaryTopicOf
is dbo:wikiPageWikiLink of
is foaf:primaryTopic of
Powered by OpenLink Virtuoso    This material is Open Knowledge     W3C Semantic Web Technology     This material is Open Knowledge    Valid XHTML + RDFa
This content was extracted from Wikipedia and is licensed under the Creative Commons Attribution-ShareAlike 3.0 Unported License