An Entity of Type: infrastructure, from Named Graph: http://dbpedia.org, within Data Space: dbpedia.org

The Simplício Hydroelectric Complex is located on the Paraíba do Sul river on the border of Rio de Janeiro and Minas Gerais states in Brazil. Supported by the Anta Dam, it transfers water through a 26 kilometres (16 mi) circuit to a downstream power plant. After years of delay and a cost of US$2 billion, the power complex became operational in June 2013.

Property Value
dbo:abstract
  • The Simplício Hydroelectric Complex is located on the Paraíba do Sul river on the border of Rio de Janeiro and Minas Gerais states in Brazil. Supported by the Anta Dam, it transfers water through a 26 kilometres (16 mi) circuit to a downstream power plant. After years of delay and a cost of US$2 billion, the power complex became operational in June 2013. (en)
dbo:buildingStartDate
  • January 2007
dbo:buildingStartYear
  • 2007-01-01 (xsd:gYear)
dbo:country
dbo:lake
dbo:location
dbo:openingYear
  • 2013-01-01 (xsd:gYear)
dbo:owner
dbo:part
dbo:status
  • O
dbo:wikiPageID
  • 30276611 (xsd:integer)
dbo:wikiPageLength
  • 7287 (xsd:nonNegativeInteger)
dbo:wikiPageRevisionID
  • 894085119 (xsd:integer)
dbo:wikiPageWikiLink
dbp:constructionBegan
  • January 2007 (en)
dbp:cost
  • $2 billion USD (en)
dbp:country
dbp:location
dbp:lowerResName
  • five reservoirs (en)
dbp:name
  • Simplício Hydroelectric Complex (en)
dbp:nameOfficial
  • Hidrelétrico UHE Simplício (en)
dbp:opening
  • June 2013 (en)
dbp:owner
dbp:plantTurbines
  • 2 (xsd:integer)
  • Anta Dam: (en)
  • Main powerhouse: 3 x Francis-type (en)
dbp:resName
  • Complex contains (en)
dbp:status
  • O (en)
dbp:wikiPageUsesTemplate
dcterms:subject
georss:point
  • -22.034166666666668 -43.00083333333333
rdf:type
rdfs:comment
  • The Simplício Hydroelectric Complex is located on the Paraíba do Sul river on the border of Rio de Janeiro and Minas Gerais states in Brazil. Supported by the Anta Dam, it transfers water through a 26 kilometres (16 mi) circuit to a downstream power plant. After years of delay and a cost of US$2 billion, the power complex became operational in June 2013. (en)
rdfs:label
  • Simplício Hydroelectric Complex (en)
owl:sameAs
geo:geometry
  • POINT(-43.000831604004 -22.03416633606)
geo:lat
  • -22.034166 (xsd:float)
geo:long
  • -43.000832 (xsd:float)
prov:wasDerivedFrom
foaf:isPrimaryTopicOf
foaf:name
  • Simplício Hydroelectric Complex (en)
  • Hidrelétrico UHE Simplício (en)
is dbo:wikiPageRedirects of
is dbo:wikiPageWikiLink of
is dbp:aux of
is foaf:primaryTopic of
Powered by OpenLink Virtuoso    This material is Open Knowledge     W3C Semantic Web Technology     This material is Open Knowledge    Valid XHTML + RDFa
This content was extracted from Wikipedia and is licensed under the Creative Commons Attribution-ShareAlike 3.0 Unported License