Lake Bonney Wind Farm, in South Australia, was built in three stages. Stage 1 comprises 46 turbines each having a rated capacity of 1.75 MW (total 80.5 MW) and was finished in March 2005. Construction of Stage 2 began in November 2006 and was finished around April 2008. Stage 2 comprises 53 turbines of 3 MW (total 159 MW). Stage 3 comprises 13 turbines of 3 MW of total 39 MW). Stage 3 construction commenced in February 2009 and was commissioned in September 2009.

Property Value
dbo:abstract
  • Lake Bonney Wind Farm, in South Australia, was built in three stages. Stage 1 comprises 46 turbines each having a rated capacity of 1.75 MW (total 80.5 MW) and was finished in March 2005. Construction of Stage 2 began in November 2006 and was finished around April 2008. Stage 2 comprises 53 turbines of 3 MW (total 159 MW). Stage 3 comprises 13 turbines of 3 MW of total 39 MW). Stage 3 construction commenced in February 2009 and was commissioned in September 2009. The wind farm is south of, and contiguous with, Canunda Wind Farm. Both are built along the Woakwine Range - a line of stabilised sand dunes that once were coastal. The nearest large town is Millicent. The owner of the Lake Bonney Wind Farm is Infigen Energy, previously known as Babcock and Brown Wind Partners. Wind turbines are serviced under a post-warranty service agreement by the Original Equipment Manufacturer Vestas. (en)
dbo:capacityFactor
  • 34.000000 (xsd:float)
dbo:location
dbo:owner
dbo:status
  • O
dbo:thumbnail
dbo:wikiPageExternalLink
dbo:wikiPageID
  • 10638743 (xsd:integer)
dbo:wikiPageLength
  • 6167 (xsd:nonNegativeInteger)
dbo:wikiPageRevisionID
  • 1042447590 (xsd:integer)
dbo:wikiPageWikiLink
dbp:cost
  • (en)
  • 7.0E8
dbp:country
  • Australia (en)
dbp:imageCaption
  • Early morning at Lake Bonney wind farm (en)
dbp:location
dbp:name
  • Lake Bonney Wind Farm (en)
dbp:owner
dbp:psElectricalCapFac
  • 34.0
dbp:psElectricalCapacity
  • 278.500000 (xsd:double)
dbp:psStorageCapacity
  • 52 (xsd:integer)
dbp:psUnitsManuModel
dbp:psUnitsOperational
  • 112 (xsd:integer)
dbp:status
  • O (en)
dbp:website
dbp:wikiPageUsesTemplate
dbp:windFarmType
  • Onshore (en)
dcterms:subject
georss:point
  • -37.76 140.4
rdf:type
rdfs:comment
  • Lake Bonney Wind Farm, in South Australia, was built in three stages. Stage 1 comprises 46 turbines each having a rated capacity of 1.75 MW (total 80.5 MW) and was finished in March 2005. Construction of Stage 2 began in November 2006 and was finished around April 2008. Stage 2 comprises 53 turbines of 3 MW (total 159 MW). Stage 3 comprises 13 turbines of 3 MW of total 39 MW). Stage 3 construction commenced in February 2009 and was commissioned in September 2009. (en)
rdfs:label
  • Lake Bonney Wind Farm (en)
owl:sameAs
geo:geometry
  • POINT(140.39999389648 -37.759998321533)
geo:lat
  • -37.759998 (xsd:float)
geo:long
  • 140.399994 (xsd:float)
prov:wasDerivedFrom
foaf:depiction
foaf:homepage
foaf:isPrimaryTopicOf
foaf:name
  • Lake Bonney Wind Farm (en)
is dbo:wikiPageRedirects of
is dbo:wikiPageWikiLink of
is foaf:primaryTopic of
Powered by OpenLink Virtuoso    This material is Open Knowledge     W3C Semantic Web Technology     This material is Open Knowledge    Valid XHTML + RDFa
This content was extracted from Wikipedia and is licensed under the Creative Commons Attribution-ShareAlike 3.0 Unported License