The Félou Hydroelectric Plant is a hydroelectric installation at the Félou Falls on the Sénégal River in Mali. It has three water turbines capable of generating 62.3 MW. The current power station replaced an older one built in the 1920s. Construction of the new power station began in October 2009 and was financed by the World Bank. It is the third Senegal River Basin Development Authority project on the river and was completed in 2014. The existing weir was refurbished with the previous 2 metres (6.6 ft) height maintained. In 1927, the previous hydroelectric power station was commissioned. It was refurbished in 1992 and had an installed capacity of 600 kW.

Property Value
dbo:Infrastructure/length
  • 0.945
dbo:abstract
  • Das Kraftwerk Félou (französisch aménagement hydroélectrique de Félou) ist ein Wasserkraftwerk in der Region Kayes, Mali, das am Senegal bei den Wasserfällen von Félou liegt. Die Stadt Kayes befindet sich ungefähr 15 km flussabwärts vom Kraftwerk, die Manantali-Talsperre ca. 200 km flussaufwärts. Das Kraftwerk wurde von 2009 bis 2013 errichtet und im Dezember 2013 in Betrieb genommen. Es ist im Besitz der Société de Gestion de l’Energie de Manantali (SOGEM) und wird auch von SOGEM betrieben. (de)
  • The Félou Hydroelectric Plant is a hydroelectric installation at the Félou Falls on the Sénégal River in Mali. It has three water turbines capable of generating 62.3 MW. The current power station replaced an older one built in the 1920s. Construction of the new power station began in October 2009 and was financed by the World Bank. It is the third Senegal River Basin Development Authority project on the river and was completed in 2014. The existing weir was refurbished with the previous 2 metres (6.6 ft) height maintained. In 1927, the previous hydroelectric power station was commissioned. It was refurbished in 1992 and had an installed capacity of 600 kW. At maximum output the three 21 MW turbines pass a total of 500 cubic metres per second (18,000 cu ft/s) of water. Between August and November the water flowing in the river generally exceeds this value allowing the plant to operate at full capacity and the excess water to pass over the weir. During the dry season (December to July) the electricity generated is reduced to about a third of the maximum output as the flow of water is limited to the 150–200 cubic metres per second (5,300–7,100 cu ft/s) released from the Manantali Dam. The total estimated cost is 241 million US dollars. The construction of the plant was completed in 2014. (en)
  • La centrale idroelettrica di Félou è un'installazione idroelettrica presso le sul fiume Senegal in Mali. È dotata di tre turbine, capaci di generare 62,3 MW. (it)
  • Felou Hydroelectric Power Plant är ett vattenkraftverk i västra Mali. Det ligger i regionen Kayes, 400 km nordväst om huvudstaden Bamako. Felou Hydroelectric Power Plant ligger 42 meter över havet. Runt Felou Hydroelectric Power Plant är det ganska glesbefolkat, med 23 invånare per kvadratkilometer. Närmaste större samhälle är Kayes, 14 km nordväst om Felou Hydroelectric Power Plant. (sv)
  • ГЕС Felou — гідроелектростанція на крайньому заході Малі. Розташована нижче від ГЕС Мананталі є нижній ступінь у каскаді сточища річки Сенегал варто відзначити, що станом на другу половину 2010-х між цими двома станціями будують ГЕС Гуїна). У межах проєкту в руслі Сенегалу перед порогом Felou спорудили невисоку (до 2 метрів) греблю довжиною 945 метрів, яка відводить воду до спорудженого на лівобережжі дериваційного каналу довжиною близько 300 метрів, що прямує до розташованого нижче порогу машинного залу. Останній обладнали трьома бульбовими турбінами загальною потужністю 62,3 МВт, які при напорі у 13,8 м забезпечують середньорічне виробництво електроенергії на рівні 335 млн кВт·год. За машинним залом слідує короткий — близько 100 метрів — відвідний канал. Видача продукції відбувається по ЛЕП, що працює під напругою 225 кВ. Проєкт, як і всі інші ГЕС каскаду, реалізувала Організація з розвитку річки Сенегал (Organisation pour la mise en valeur du fleuve Sénégal, OMVS), створена спільно Малі, Сенегалом та Мавританією. Відповідно, вироблена електроенергія ділиться між цими трьома країнами. (uk)
dbo:buildingStartDate
  • 2009
dbo:buildingStartYear
  • 2009-01-01 (xsd:gYear)
dbo:country
dbo:description
  • Weir (en)
dbo:height
  • 2.000000 (xsd:double)
dbo:length
  • 945.000000 (xsd:double)
dbo:location
dbo:openingYear
  • 1927-01-01 (xsd:gYear)
dbo:part
dbo:purpose
  • Power
dbo:river
dbo:status
  • O
dbo:thumbnail
dbo:wikiPageID
  • 44918700 (xsd:integer)
dbo:wikiPageLength
  • 5748 (xsd:nonNegativeInteger)
dbo:wikiPageRevisionID
  • 1098102969 (xsd:integer)
dbo:wikiPageWikiLink
dbp:constructionBegan
  • 2009 (xsd:integer)
dbp:cost
  • 242000000 (xsd:integer)
dbp:country
dbp:damCrosses
dbp:damType
  • Weir (en)
dbp:imageCaption
  • Plant in 2014 (en)
dbp:location
dbp:locationMap
  • Mali (en)
dbp:name
  • Félou Weir (en)
dbp:nameOfficial
  • Félou Hydroelectric Plant (en)
dbp:plantCommission
  • 2014 (xsd:integer)
dbp:plantOperator
  • Operator: ESKOM (en)
  • Owner: Société de Gestion de l'Energie de Manantali (en)
dbp:plantTurbines
  • 3 (xsd:integer)
dbp:plantType
  • R (en)
dbp:purpose
  • Power (en)
dbp:status
  • O (en)
dbp:wikiPageUsesTemplate
dcterms:subject
gold:hypernym
georss:point
  • 14.35361111111111 -11.345277777777778
rdf:type
rdfs:comment
  • Das Kraftwerk Félou (französisch aménagement hydroélectrique de Félou) ist ein Wasserkraftwerk in der Region Kayes, Mali, das am Senegal bei den Wasserfällen von Félou liegt. Die Stadt Kayes befindet sich ungefähr 15 km flussabwärts vom Kraftwerk, die Manantali-Talsperre ca. 200 km flussaufwärts. Das Kraftwerk wurde von 2009 bis 2013 errichtet und im Dezember 2013 in Betrieb genommen. Es ist im Besitz der Société de Gestion de l’Energie de Manantali (SOGEM) und wird auch von SOGEM betrieben. (de)
  • La centrale idroelettrica di Félou è un'installazione idroelettrica presso le sul fiume Senegal in Mali. È dotata di tre turbine, capaci di generare 62,3 MW. (it)
  • Felou Hydroelectric Power Plant är ett vattenkraftverk i västra Mali. Det ligger i regionen Kayes, 400 km nordväst om huvudstaden Bamako. Felou Hydroelectric Power Plant ligger 42 meter över havet. Runt Felou Hydroelectric Power Plant är det ganska glesbefolkat, med 23 invånare per kvadratkilometer. Närmaste större samhälle är Kayes, 14 km nordväst om Felou Hydroelectric Power Plant. (sv)
  • The Félou Hydroelectric Plant is a hydroelectric installation at the Félou Falls on the Sénégal River in Mali. It has three water turbines capable of generating 62.3 MW. The current power station replaced an older one built in the 1920s. Construction of the new power station began in October 2009 and was financed by the World Bank. It is the third Senegal River Basin Development Authority project on the river and was completed in 2014. The existing weir was refurbished with the previous 2 metres (6.6 ft) height maintained. In 1927, the previous hydroelectric power station was commissioned. It was refurbished in 1992 and had an installed capacity of 600 kW. (en)
  • ГЕС Felou — гідроелектростанція на крайньому заході Малі. Розташована нижче від ГЕС Мананталі є нижній ступінь у каскаді сточища річки Сенегал варто відзначити, що станом на другу половину 2010-х між цими двома станціями будують ГЕС Гуїна). Видача продукції відбувається по ЛЕП, що працює під напругою 225 кВ. Проєкт, як і всі інші ГЕС каскаду, реалізувала Організація з розвитку річки Сенегал (Organisation pour la mise en valeur du fleuve Sénégal, OMVS), створена спільно Малі, Сенегалом та Мавританією. Відповідно, вироблена електроенергія ділиться між цими трьома країнами. (uk)
rdfs:label
  • Kraftwerk Félou (de)
  • Félou Hydroelectric Plant (en)
  • Centrale idroelettrica di Félou (it)
  • Felou Hydroelectric Power Plant (sv)
  • ГЕС Felou (uk)
owl:sameAs
geo:geometry
  • POINT(-11.345277786255 14.353610992432)
geo:lat
  • 14.353611 (xsd:float)
geo:long
  • -11.345278 (xsd:float)
prov:wasDerivedFrom
foaf:depiction
foaf:isPrimaryTopicOf
foaf:name
  • Félou Hydroelectric Plant (en)
  • Félou Weir (en)
is dbo:wikiPageRedirects of
is dbo:wikiPageWikiLink of
is foaf:primaryTopic of
Powered by OpenLink Virtuoso    This material is Open Knowledge     W3C Semantic Web Technology     This material is Open Knowledge    Valid XHTML + RDFa
This content was extracted from Wikipedia and is licensed under the Creative Commons Attribution-ShareAlike 3.0 Unported License