- United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332 (1956), is a United States Supreme Court case in which the Court interpreted the Natural Gas Act of 1938 (NGA) as not allowing a gas supply company to unilaterally modify rates in a natural gas supply contract by filing a new rate schedule with the Federal Power Commission (FPC). Mobile Gas and its companion case Federal Power Commission v. Sierra Pacific Power Co. established the Mobile-Sierra presumption which holds that an electricity or natural gas supply rate established resulting from a freely negotiated contract is presumed to be "just and reasonable" and thus acceptable under the NGA or Federal Power Act (FPA). (en)
|
dbo:wikiPageExternalLink
| |
dbo:wikiPageID
| |
dbo:wikiPageLength
|
- 11260 (xsd:nonNegativeInteger)
|
dbo:wikiPageRevisionID
| |
dbo:wikiPageWikiLink
| |
dbp:arguedatea
|
- 0001-11-07 (xsd:gMonthDay)
|
dbp:arguedateb
| |
dbp:argueyear
| |
dbp:case
|
- United Gas Pipe Line Co. v. Mobile Gas Service Corp., (en)
|
dbp:courtlistener
| |
dbp:decidedate
|
- 0001-02-27 (xsd:gMonthDay)
|
dbp:decideyear
| |
dbp:findlaw
| |
dbp:fullname
|
- United Gas Pipe Line Co. v. Mobile Gas Service Corp., et al. (en)
|
dbp:googlescholar
| |
dbp:holding
|
- A gas company could not unilaterally modify a rate in a contract on file with the Federal Power Commission (en)
|
dbp:joinmajority
| |
dbp:justia
| |
dbp:lawsapplied
|
- National Gas Act, 15 U.S.C. ยง 717 et seq. (en)
|
dbp:litigants
|
- United Gas Pipe Line Co. v. Mobile Gas Service Corp. (en)
|
dbp:loc
| |
dbp:majority
| |
dbp:parallelcitations
| |
dbp:prior
| |
dbp:uspage
| |
dbp:usvol
| |
dbp:wikiPageUsesTemplate
| |
dcterms:subject
| |
rdf:type
| |
rdfs:comment
|
- United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332 (1956), is a United States Supreme Court case in which the Court interpreted the Natural Gas Act of 1938 (NGA) as not allowing a gas supply company to unilaterally modify rates in a natural gas supply contract by filing a new rate schedule with the Federal Power Commission (FPC). Mobile Gas and its companion case Federal Power Commission v. Sierra Pacific Power Co. established the Mobile-Sierra presumption which holds that an electricity or natural gas supply rate established resulting from a freely negotiated contract is presumed to be "just and reasonable" and thus acceptable under the NGA or Federal Power Act (FPA). (en)
|
rdfs:label
|
- United Gas Pipe Line Co. v. Mobile Gas Service Corp. (en)
|
owl:sameAs
| |
prov:wasDerivedFrom
| |
foaf:isPrimaryTopicOf
| |
foaf:name
|
- (en)
- United Gas Pipe Line Co. v. Mobile Gas Service Corp., et al. (en)
|
is dbo:wikiPageRedirects
of | |
is dbo:wikiPageWikiLink
of | |
is foaf:primaryTopic
of | |