Federal Power Commission v. Tuscarora Indian Nation, 362 U.S. 99 (1960), was a case decided by the United States Supreme Court which determined that the Federal Power Commission was authorized to take lands owned by the Tuscarora Indian tribe by eminent domain under the Federal Power Act for a hydroelectric power project, upon payment of just compensation.
Attributes | Values |
---|
rdf:type
| |
rdfs:label
| - Federal Power Commission v. Tuscarora Indian Nation (en)
|
rdfs:comment
| - Federal Power Commission v. Tuscarora Indian Nation, 362 U.S. 99 (1960), was a case decided by the United States Supreme Court which determined that the Federal Power Commission was authorized to take lands owned by the Tuscarora Indian tribe by eminent domain under the Federal Power Act for a hydroelectric power project, upon payment of just compensation. (en)
|
foaf:name
| - (en)
- Federal Power Commission v. Tuscarora Indian Nation (en)
|
dcterms:subject
| |
Wikipage page ID
| |
Wikipage revision ID
| |
Link from a Wikipage to another Wikipage
| |
Link from a Wikipage to an external page
| |
sameAs
| |
dbp:wikiPageUsesTemplate
| |
Dissent
| |
JoinDissent
| |
JoinMajority
| - Warren, Frankfurter, Clark, Harlan, Stewart (en)
|
LawsApplied
| |
oyez
| |
ParallelCitations
| |
Prior
| - United States Court of Appeals for the District of Columbia Circuit (en)
|
USPage
| |
USVol
| |
ArgueDate
| |
ArgueYear
| |
case
| - Federal Power Commission v. Tuscarora Indian Nation, (en)
|
DecideDate
| |
DecideYear
| |
fullname
| - Federal Power Commission v. Tuscarora Indian Nation (en)
|
Holding
| - The Federal Power Commission did indeed have the right to seize land from the Tuscarora Indian Tribe with just compensation. (en)
|
justia
| |
majority
| |
loc
| |
has abstract
| - Federal Power Commission v. Tuscarora Indian Nation, 362 U.S. 99 (1960), was a case decided by the United States Supreme Court which determined that the Federal Power Commission was authorized to take lands owned by the Tuscarora Indian tribe by eminent domain under the Federal Power Act for a hydroelectric power project, upon payment of just compensation. (en)
|
Concurrence
| |
prov:wasDerivedFrom
| |
page length (characters) of wiki page
| |
foaf:isPrimaryTopicOf
| |
is Link from a Wikipage to another Wikipage
of | |